The project sponsor has just requested a status report be emailed to all project stakeholders every
two weeks. Which of the following documents needs to be updated?
A.
Communications plan
B.
Quality plan
C.
Stakeholder analysis report
D.
Work Breakdown Structure (WBS)
Explanation: