which of the following documents should the project manager record this information?

A key stakeholder on a project advises the project manager that there is a component of the
project that has yet to be decided. They are concerned that their needs regarding this component
will not be addressed. In which of the following documents should the project manager record this
information?

A key stakeholder on a project advises the project manager that there is a component of the
project that has yet to be decided. They are concerned that their needs regarding this component
will not be addressed. In which of the following documents should the project manager record this
information?

A.
Lessons learned

B.
Issue log

C.
Statement of Work (SOW)

D.
Project charter

Explanation: