The amount of time ahead or behind schedule on a project is called the:

The amount of time ahead or behind schedule on a project is called the:

The amount of time ahead or behind schedule on a project is called the:

A.
schedule baseline.

B.
schedule performance index.

C.
estimate to complete.

D.
schedule variance.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *