Which of the following should be the NEXT step for the project manager?

There are three teams assigned to the same project. Two of the project teams are ahead of
schedule; however, the product does not meet the needed quality standards. The third project
team is behind schedule, but their product meets the quality standards. Which of the following
should be the NEXT step for the project manager?

There are three teams assigned to the same project. Two of the project teams are ahead of
schedule; however, the product does not meet the needed quality standards. The third project
team is behind schedule, but their product meets the quality standards. Which of the following
should be the NEXT step for the project manager?

A.
Inform the stakeholders that the project is behind schedule.

B.
Meet with the teams to clarify the schedule and the quality standards expected.

C.
Crash the schedule to meet the project timeline.

D.
Fast track the schedule to complete the project on time without impacting the quality of the
product.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *