A project manager has to complete an asset inventory project for a large corporation. Several
departments have refused to allow access to the equipment to complete the project. The project
manager should update which of the following?
A.
Change control form
B.
Risk register
C.
Work Breakdown Structure (WBS)
D.
Issues log
Explanation: