Changing the project schedule to prevent a known risk is an example of which of the following risk
responses?
A.
Mitigation
B.
Avoidance
C.
Acceptance
D.
Transference
Explanation:
Changing the project schedule to prevent a known risk is an example of which of the following risk
responses?
Changing the project schedule to prevent a known risk is an example of which of the following risk
responses?
A.
Mitigation
B.
Avoidance
C.
Acceptance
D.
Transference
Explanation: