which of the following risk responses?

Changing the project schedule to prevent a known risk is an example of which of the following risk
responses?

Changing the project schedule to prevent a known risk is an example of which of the following risk
responses?

A.
Mitigation

B.
Avoidance

C.
Acceptance

D.
Transference

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *