Which of the following documents would the project manager update?

The change control board has just approved a request to modify the sampling technique for a
project. Which of the following documents would the project manager update?

The change control board has just approved a request to modify the sampling technique for a
project. Which of the following documents would the project manager update?

A.
Risk management plan

B.
Quality management plan

C.
Communication management plan

D.
Scope management plan

Explanation: