The project is behind schedule. A project team member has analyzed the work performance
information and has not created the weekly status update because they are uncertain when the
update should be completed. Which of the following documents should the team member consult?
A.
Communication plan
B.
Risk plan
C.
Scope plan
D.
Quality plan