This can MOST likely be attributed to:

An experienced team member comes to the project manager to report that they are uncertain of
the project requirements. This can MOST likely be attributed to:

An experienced team member comes to the project manager to report that they are uncertain of
the project requirements. This can MOST likely be attributed to:

A.
a poorly decomposed WBS.

B.
inadequate schedule analysis.

C.
inadequate resource management.

D.
improper risk planning.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *