An experienced team member comes to the project manager to report that they are uncertain of
the project requirements. This can MOST likely be attributed to:
A.
a poorly decomposed WBS.
B.
inadequate schedule analysis.
C.
inadequate resource management.
D.
improper risk planning.
Explanation: