A project manager has noted that a vendor is providing a poor quality product. The vendor states
that its products meet the quality standards outlined in the current contract. Which of the following
documents outline the contractual requirements?
A.
The statement of work (SOW)
B.
The milestone schedule
C.
The request for proposal (RFP)
D.
The work breakdown structure (WBS)
Explanation: