Which of the following techniques will the project manager MOST likely use to deliver the project on time?

During the execution phase of a project, a change request has been approved to add activities to

the critical path without altering the schedule. Which of the following techniques will the project
manager MOST likely use to deliver the project on time?

During the execution phase of a project, a change request has been approved to add activities to

the critical path without altering the schedule. Which of the following techniques will the project
manager MOST likely use to deliver the project on time?

A.
Bottom-up estimating

B.
Rolling wave planning

C.
Resource leveling

D.
Fast tracking

Explanation: