Two SMEs disagree with the designed plan for a particular component. The project will be delayed
if the plan is not approved today. The project manager demands the SMEs work together to
incorporate their modifications by the close of business today. Which of the following resolution
techniques was used?
A.
Negotiating
B.
Forcing
C.
Smoothing
D.
Compromise
Explanation: