At a project milestone meeting, the project sponsor asked about a deliverable that is not on the
project plan. Which of the following should the project manager do to compensate for this unmet
expectation?
A.
Review the scope with the vendor.
B.
Review the scope with the customer.
C.
Review the scope with the team.
D.
Review the scope with the sponsor.