Which of the following is an input to a work breakdown structure (WBS)?
A.
Performance reports
B.
Stakeholder analysis
C.
Project scope statement
D.
Variance analysis
Explanation:
Which of the following is an input to a work breakdown structure (WBS)?
Which of the following is an input to a work breakdown structure (WBS)?
A.
Performance reports
B.
Stakeholder analysis
C.
Project scope statement
D.
Variance analysis
Explanation: