Which of the following is an input to a work breakdown structure (WBS)?

Which of the following is an input to a work breakdown structure (WBS)?

Which of the following is an input to a work breakdown structure (WBS)?

A.
Performance reports

B.
Stakeholder analysis

C.
Project scope statement

D.
Variance analysis

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *

sixteen − fourteen =