The project manager should ask the stakeholder to FIRST:

A stakeholder asks the project manager to finish a project early. The project manager should ask
the stakeholder to FIRST:

A stakeholder asks the project manager to finish a project early. The project manager should ask
the stakeholder to FIRST:

A.
speak to the other stakeholders to get their opinion.

B.
complete a change request form.

C.
speak to the project sponsor.

D.
consider how this might impact the quality of the product.

Explanation: