A stakeholder asks the project manager to finish a project early. The project manager should ask
the stakeholder to FIRST:
A.
speak to the other stakeholders to get their opinion.
B.
complete a change request form.
C.
speak to the project sponsor.
D.
consider how this might impact the quality of the product.
Explanation: