All of the following are taken into account when determining the critical path EXCEPT:

All of the following are taken into account when determining the critical path EXCEPT:

All of the following are taken into account when determining the critical path EXCEPT:

A.
Late start and finish dates.

B.
Activity durations.

C.
Early start and finish dates.

D.
Resource limitations.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *