If accepted, this request is an example of:

A project sponsor has requested that the training be delivered in parallel to a project’s
implementation in order to ensure the project is delivered on schedule. If accepted, this request is
an example of:

A project sponsor has requested that the training be delivered in parallel to a project’s
implementation in order to ensure the project is delivered on schedule. If accepted, this request is
an example of:

A.
the critical path method.

B.
crashing.

C.
fast-tracking.

D.
rolling wave planning.

Explanation: