Which of the following conclusions can be drawn when a project has a CPI of 1.2?

Which of the following conclusions can be drawn when a project has a CPI of 1.2?

Which of the following conclusions can be drawn when a project has a CPI of 1.2?

A.
The project is taking longer than the estimated schedule.

B.
The project is costing less than the estimated budget.

C.
The project is taking less time than the estimated schedule.

D.
The project is costing more than the estimated budget.

Explanation: