Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of $10,000 and an ETC of $50,000?

Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of
$10,000 and an ETC of $50,000?

Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of
$10,000 and an ETC of $50,000?

A.
$90,000

B.
$140,000

C.
$150,000

D.
$160,000

E.
The project is taking longer than the estimated schedule.

F.
The project is costing less than the estimated budget.

G.
The project is taking less time than the estimated schedule.

H.
The project is costing more than the estimated budget.

Explanation: