Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?

Which of the following resource leveling techniques describes schedule compression by
performing activities concurrently?

Which of the following resource leveling techniques describes schedule compression by
performing activities concurrently?

A.
Exploiting

B.
Crashing

C.
Optimizing

D.
Fast tracking

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *

10 − eight =