Which of the following is an important aspect of formal project closure?
A.
Assign resources to the next project.
B.
Analyze quality and ensure standards are being met.
C.
Document lessons learned for use in future projects.
D.
Modify the WBS to include all the change requests that occurred during the project.
Explanation: