In order to prepare a project charter, which of the following items are required for the pre-project
setup?
A.
Assumptions, constraints, project deliverables, and all resources required for the project.
B.
Client name, client project manager, organization project manager, and a complete project
budget.
C.
Direction from team members, development methodology, and staff requirements.
D.
Business need, assumptions, constraints, project deliverables, and staff requirements.
Explanation: