Which of the following is the purpose of a milestone schedule?
A.
A detailed summary of the project milestones that need to be achieved.
B.
A summary level timetable of the major project milestones.
C.
A summary of the anticipated milestones and the issues identified for the project.
D.
A detailed summary of the anticipated milestones and risks identified for the project.
Explanation: