Which of the following are characteristics of an approved project charter? (Select Two).
A.
Provides the prioritization of work from the stakeholders.
B.
Defines the project managers authority.
C.
Identifies what the project manager wants to derive from the project.
D.
Increases the number of just-in-time processes required to decrease scope creep.
E.
Validates the existence of a project.
Explanation: