Which of the following is the CPI of the project?

An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000.
Which of the following is the CPI of the project?

An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000.
Which of the following is the CPI of the project?

A.
$340,000

B.
1.1

C.
$10,000

D.
.91

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *