In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been
completed. The BAC is $900,000. Which of the following represents the EV of this project?
A.
$150,000
B.
$300,000
C.
$450,000
D.
$600,000
Explanation:
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been
completed. The BAC is $900,000. Which of the following represents the EV of this project?
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been
completed. The BAC is $900,000. Which of the following represents the EV of this project?
A.
$150,000
B.
$300,000
C.
$450,000
D.
$600,000
Explanation: