The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be
determined from this information?
A.
The project costs are currently under-budget.
B.
The AC is less than the EV.
C.
The EV is higher than the AC.
D.
The project costs are currently over-budget.