In order to compare a current projects quality to that of a previously completed project, a project
manager should use which of the following techniques?

In order to compare a current projects quality to that of a previously completed project, a project
manager should use which of the following techniques?

A.
Process improvement

B.
Quality metrics

C.
Benchmarking

D.
Cost-benefit analysis

Explanation: