which of the following should the project manager do?

When a project ends unexpectedly, which of the following should the project manager do?

When a project ends unexpectedly, which of the following should the project manager do?

A.
Create an end document to add to the file before moving on to another project.

B.
Create a document identifying the negative impact of the early project ending to give to the
customers management.

C.
Perform project close out with full documentation and review.

D.
Perform a limited project close that consists of releasing team members.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *