During a status meeting, a team member informs the project manager of a possible risk. Which of
the following is the FIRST action the project manager should take?
A.
Record the risk in the risk register.
B.
Work with the team to develop a risk response.
C.
Perform an initial prioritization of the risk.
D.
Determine the probability and impact of the risk.
Explanation: