which of the following actions?

A project manager has just completed the planning of a project, but cannot start the project
execution until granted permission from the project sponsor. This is an example of which of the
following actions?

A project manager has just completed the planning of a project, but cannot start the project
execution until granted permission from the project sponsor. This is an example of which of the
following actions?

A.
Stakeholder analysis

B.
Risk assessment

C.
Audit review

D.
Phase gate

Explanation: