The change control board has approved a change to the scope of a project. Which of the following
actions should the project manager take NEXT?
A.
Obtain additional approval from the project sponsor.
B.
Discuss this change during the next status meeting.
C.
Perform a probability and impact analysis on the change.
D.
Create a plan to implement the change.
Explanation: