The project team has completed phase testing. After testing, a subject matter expert (SME)
notices that a component was skipped.
Which of the following should the project manager do?
A.
Proceed with the release and document the adjustment in the change log.
B.
Proceed with the release and tell the SME the component will be added in a special release.
C.
Delay the release until the component is tested.
D.
Schedule a meeting with the stakeholders to review the impact.
Explanation: