Which of the following risk responses is the project manager using?

A hurricane is forecasted near the corporations call center. The project manager has arranged for
a redundant call center in another location to accept calls if the corporate call center is unable to

receive calls. Which of the following risk responses is the project manager using?

A hurricane is forecasted near the corporations call center. The project manager has arranged for
a redundant call center in another location to accept calls if the corporate call center is unable to

receive calls. Which of the following risk responses is the project manager using?

A.
Avoidance

B.
Acceptance

C.
Mitigation

D.
Transference

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *

1 × 5 =