which of the following performance statistics?

A variance between the planned scheduled work and the actual work completed would initially be
highlighted in which of the following performance statistics?

A variance between the planned scheduled work and the actual work completed would initially be
highlighted in which of the following performance statistics?

A.
CV

B.
SV

C.
CPI

D.
ETC

Explanation: