Which of the following would the project manager use to document the details of the project closure?

A project is cancelled unexpectedly prior to completion. Which of the following would the project
manager use to document the details of the project closure?

A project is cancelled unexpectedly prior to completion. Which of the following would the project
manager use to document the details of the project closure?

A.
Histogram

B.
Post mortem

C.
SWOT analysis

D.
Project scope statement

Explanation: