A qualitative analysis identified a server crash as an internal project risk with a medium probability
and high adverse impact to the project. The project manager decides to manage this risk by
authorizing the purchase and installation of a tape backup unit for the server, to prevent the
potential loss of documents. Which of the following risk response strategies was applied in this
circumstance?
A.
Acceptance
B.
Transfer
C.
Mitigation
D.
Avoidance
Explanation: