Which of the following is true of fast tracking a schedule?

Which of the following is true of fast tracking a schedule?

Which of the following is true of fast tracking a schedule?

A.
Project schedule critical path will change.

B.
Project activities will be performed concurrently.

C.
Project schedule is shortened by decreasing the project scope.

D.
Project schedule lead times are increased.