A project manager is performing activity sequencing using the arrow diagramming method (ADM).
Which of the following is true of ADM?
A.
ADM can only represent finish to start dependencies.
B.
ADM cannot represent multiple successor activities.
C.
ADM can only represent activities that are on the critical path.
D.
ADM uses boxes representing activities, and arrows to represent dependencies.