Which of the following actions would require a formal project closure? (Select Two).
A.
The project is delayed indefinitely because a required vendor part cannot be delivered.
B.
The project is producing a product that is no longer compliant with new Federal regulations.
C.
The project work is completed.
D.
The project has run out of money.
E.
The project sponsor has become disinterested in the project.