A stakeholder has determined the need to update their payroll method with a new system. Which of the following is the FIRST activity the corporation should perform?
A.
Conduct a feasibility study.
B.
Determine the justification of the project.
C.
Obtain a preliminary review by the project selection committee.
D.
Determine if the project is in alignment with the companys strategic plan.