A project manager is performing activity duration estimation. This project will have conditional decisions. Which of the following tools would be the BEST to use?

A project manager is performing activity duration estimation. This project will have conditional decisions. Which of the following tools would be the BEST to use?

A.
GERT

B.
Gantt chart

C.
PERT

D.
EVM