A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?
A.
Distribute details of the change per the communication plan, and implement according to the change control process.
B.
Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.
C.
Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team members.
D.
Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.