Which of the following is the expected duration for this scheduled activity?

Given the following information: Pessimistic estimate is 30 days Most Likely estimate is 15 days Optimistic estimate is 10 days. Which of the following is the expected duration for this scheduled activity?

Given the following information: Pessimistic estimate is 30 days Most Likely estimate is 15 days Optimistic estimate is 10 days. Which of the following is the expected duration for this scheduled activity?

A.
11 days

B.
17 days

C.
25 days

D.
29 days