Which of the following is the NEXT step that the project manager should take?

A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?

A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?

A.
Construct a detailed plan to implement the change.

B.
Analyze the impact of the change request.

C.
Document the request in the change control log.

D.
Request a meeting with the project sponsor to discuss scope creep.