Which of the following documents needs to be updated?

The project sponsor has just requested a status report be emailed to all project stakeholders every two weeks. Which of the following documents needs to be updated?

The project sponsor has just requested a status report be emailed to all project stakeholders every two weeks. Which of the following documents needs to be updated?

A.
Communications plan

B.
Quality plan

C.
Stakeholder analysis report

D.
Work Breakdown Structure (WBS)



Leave a Reply 0

Your email address will not be published. Required fields are marked *