Which of the following methods is the project manager demonstrating?

A project manager is performing activity sequencing. The project manager is only using start to finish dependencies. Dummy activities are being utilized to define all logical relationships. Which of the following methods is the project manager demonstrating?

A project manager is performing activity sequencing. The project manager is only using start to finish dependencies. Dummy activities are being utilized to define all logical relationships. Which of the following methods is the project manager demonstrating?

A.
Precedence Diagramming Method (PDM)

B.
Critical Chain Method (CCM)

C.
Arrow Diagramming Method (ADM)

D.
Critical Path Method (CPM)



Leave a Reply 0

Your email address will not be published. Required fields are marked *