A project manager needs to identify uncertain events during the planning phase. Which of the following documents would be the BEST source of this information?
A.
Quality log
B.
Risk register
C.
Issues log
D.
Responsibility assignment matrix
A project manager needs to identify uncertain events during the planning phase. Which of the following documents would be the BEST source of this information?
A project manager needs to identify uncertain events during the planning phase. Which of the following documents would be the BEST source of this information?
A.
Quality log
B.
Risk register
C.
Issues log
D.
Responsibility assignment matrix