A project manager is new to an organization and is about to begin work on a $1,000,000 project. Which of the following would BEST help the project manager?
A.
Reviewing closure reports from previous projects within the organization.
B.
Asking stakeholders what standards they consider important.
C.
Developing a quality management plan.
D.
Talking to other project managers who have been with the organization for a long time.