A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?
A.
Lessons learned
B.
Issue log
C.
Statement of Work (SOW)
D.
Project charter